How to tell if an electric truck can wait for cheaper charging.
Before moving a truck’s charge to a cheaper window, check how much energy its next job needs, how long it’s plugged in and how much power the depot has available.
A cheaper charging window is only useful if the truck has enough charge when it needs to leave.
That’s one of the decisions we’ll explore in a working depot, as we set out in Friday’s trial update with Welch Group.
Picture two trucks plugging in at the end of a shift. One leaves first thing and needs most of the time it has on charge. The other has a later departure and a shorter job. The second truck may be able to wait for cheaper electricity. The first may need to start charging sooner.
Start with the energy each truck needs for its next job
The starting point is how much charge the battery already holds when the truck plugs in, known as its state of charge. Compare that with the energy the next job needs, including the fleet’s operating reserve. That tells you how much energy to add.
Then check how long the truck will actually be plugged in before departure. The full time it spends on site can include loading, unloading or time waiting for a charger. The useful window is the time the truck can spend on charge before it needs to leave.
Check what the depot can supply during cheaper hours
The depot’s other electricity use leaves only part of the connection available for charging at any given time. That spare capacity is the site’s headroom.
The timing and price of cheaper periods depend on the site’s time-of-use tariff. If several trucks wait for the same period, they may need more power together than the site can supply. Estimate how much energy each truck can receive in its window, accounting for the site limit and what the charger and vehicle can handle. A workable plan might stagger starts, prioritise the first departures or deliver part of a charge earlier.
Recheck the plan when a shift changes
A late return or a job reassignment can change which truck has time to wait. Check whether the revised plan still delivers enough energy to each truck before departure. If the available time and power fall short, spotting the gap early gives the transport team time to adjust the plan.
Working with Welch Group will help us understand how much room there is to move charging when shifts and site demand change. The evidence will help us decide what the software needs to account for and where a different schedule could reduce costs, make better use of depot power and keep trucks ready for work.
If you’d like to discuss a pilot, bring your departure times, the windows when trucks can plug in and your site’s connection capacity. We’ll look at where there’s room to move charging and where the transport plan sets a tighter limit.