Depot planning

What to bring to your first electric truck depot assessment.

Bring your shift records, meter data and site limits together to see when trucks can charge and how much power they’ll have before they need to leave.

By Alex Baker, Chief Commercial Officer

Before you price chargers, put the transport plan and the site’s electricity demand next to each other. A truck can spend the night at the depot and still have less time to charge than the shift sheet suggests. The power available when it plugs in can also be very different from the power available later that night.

Start with one depot and the first trucks you want to run there. Pull the transport and meter records for the same representative week. Bring an example of your busiest shift too, and flag anything seasonal that the week misses.

DEPOT ASSESSMENTIllustrative
An electric truck depotIsometric drawing of a depot building with loading bays, six trucks beside chargers and an electrical connection at the edge of the yard.010203040506010203040506

Check when trucks can move from loading to a charger and how much of the depot’s power is available at that point.

The checklist for your first assessment

  • Transport planner. Bring the vehicle list, route or duty records, actual return times and the next planned departures. Include the shifts with late returns, back-to-back jobs or little time between them.
  • Fleet or yard team. Bring the earliest time each truck can get to a charger after unloading, checks and shunting. For electric trucks already on site, export charging sessions and arrival battery levels where available. For a planned fleet, bring the vehicle models and route energy estimates, with the assumptions behind them.
  • Facilities or electrical lead. Bring the connection agreement, half-hourly electricity import readings and any tighter site or equipment limits. Include the charger locations, connector types, power ratings and which charge points share power. For proposed chargers, bring the layout and specification.
  • Energy or finance team. Bring the current electricity contract and the rates that change by time of day, if any. A monthly bill gives you a cost baseline. The tariff schedule shows what moving a particular charging session could change.

Record when a truck can actually plug in

Use the departure time and the energy needed for the next job, including the fleet’s operating reserve. For an electric truck already in service, compare that requirement with how much charge it has when it plugs in, its state of charge.

The charging window starts when a truck can reach a compatible charger. In this example the truck has to finish unloading and wait for the bay before anyone can plug it in. If that delay happens most nights, put it into the plan.

01 / CHARGING WINDOW

Parked for 12 hours. Plugged in for 9.

Returns
18:00
Plugs in
21:00
Departs
06:00
3 hours loading and waiting9 hours available to charge

Illustrative shift. The truck stays plugged in until departure.

Put site demand against the same shift

The connection agreement gives you the site’s agreed supply capacity. Ask the site’s electrical lead to confirm the working limit for charging and check for tighter limits within the depot. If the limit is in kVA and the meter export is in kW or kWh, ask them to put the figures on a comparable basis.

Look at the demand in the hours the trucks can actually plug in. The spare capacity, or headroom, changes as the rest of the depot draws power. If the meter data already includes EV charging, bring the matching charger records so the assessment can separate existing charging from the other site load.

02 / SITE DEMAND

The power left for charging changes overnight

300 kW assumed site operating limit

  • 21:00 to 21:3080 kW spare

    220 kW already in use

  • 00:00 to 00:30210 kW spare

    90 kW already in use

Illustrative half-hour averages. Spare power is the assumed site limit less existing demand. Short peaks, safety margins and limits on charging equipment can reduce what trucks can draw.

Spare site power is shared across the depot. The power a particular truck can use also depends on its charger, the vehicle and what else is charging. Put that together with the tariff to work out which trucks can wait for cheaper electricity.

Ask what fits on the busiest shift

Start with the first set of trucks you want to deploy. Check whether they can get enough energy before departure using the chargers, time and power available. Run the check again for a busy shift with a late return or a charger out of service. If the plan falls short, work out whether the issue is time on charge, access to a charger or available power. Each points to a different change.

Start with a snapshot of your depot data

We’re working with our first pilot customers to see how much of this assessment we can do with the data fleets already collect. A transport management system (TMS) can show planned duties and departures. Vehicle telematics can show when trucks actually return and, where the data is available, how much charge they have left. The aim is to line up those records with charger sessions, site demand and electricity prices for the same period.

If you’re interested in becoming an early TOGL customer, we’d be happy to talk. We can start with a short, representative snapshot from one depot, using the records you already have. That gives us an initial estimate of where TOGL could reduce charging costs or make better use of the available power while keeping trucks ready for their shifts.

That first look helps you decide if the potential benefit is worth pursuing and helps us see whether we have the data and equipment access to run a useful pilot. If it makes sense for both of us, we’ll agree what to compare against and measure charging cost, peak site demand and whether trucks have enough charge when they leave.

For the wider investment decision, see planning your next electric truck depot.

For related work on fleet charging and site demand, see the Optimise Prime depot trial data and UK Power Networks’ Future Fleet project.